[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117710,789,1,"单选题","根据《建设工程施工合同（示范文本）》（GF-2013-0201），发包人有权书面通知承包人更换其认为不称职的项目经理，承包人应在接到第二次更换通知的（）天内进行更换。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","15",{"key":22,"text":23,"correct":24},"D","28",true,"2021\u002F2020教材P31页 发包人有权书面通知承包人更换其认为不称职的项目经理，承包人应在接到更换通知后的14天内向发包人提出书面的改进报告，发包人收到报告后仍要求更换的，承包人应在第二次更换通知的28天内进行更换。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]