[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117709,789,1,"单选题","项目管理目标责任书应在项目实施之前，由（）或其授权人与项目经理协商制定.",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业董事长",false,{"key":16,"text":17,"correct":18},"B","企业法定代表人",true,{"key":20,"text":21,"correct":14},"C","企业总经理",{"key":23,"text":24,"correct":14},"D","分管生产经营的副经理","2021\u002F2020教材P33页 项目管理目标责任书应在项目实施之前，由法定代表人或其授权人与项目经理协商制定",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]