[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117665,789,1,"单选题","承包人需要更换项目经理的，应提前( )天书面通知发包人和监理人，并征得发包人书面同意。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","28","2021\u002F2020教材P31页 3.2.3承包人需要更换项目经理的，应提前14天书面通知发包人和监理人，并征得发包人书面同意。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]