[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117663,789,1,"单选题","在项目实施过程过程动态控制工作的第一步的工作是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目决策策划",false,{"key":16,"text":17,"correct":14},"B","制定纠偏措施",{"key":19,"text":20,"correct":14},"C","分解项目目标",{"key":22,"text":23,"correct":24},"D","收集实际数据",true,"2021\u002F2020教材P27页 2. 在项目实施过程中如设计过程中、招投标过程中和施工过程中等）对项目目标进行动态跟踪和控制(1)收集项目目标的实际值，如实际投资\u002F成本、实际施工进度和施工的质量状况等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]