[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117662":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117662,789,1,"单选题","进度的控制周期应视项目的规模和特点而定，一般的项目控制周期为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一周",false,{"key":16,"text":17,"correct":18},"B","一个月",true,{"key":20,"text":21,"correct":14},"C","一个季度",{"key":23,"text":24,"correct":14},"D","一旬","2021\u002F2020教材P29页 进度控制周期应视项目的规模和特点而定，一般的项目控制周期为一个月，对于重要的项目，控制周期可定为一旬或一周等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]