[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117658,789,1,"单选题","下列进度控制措施中，属于组织措施的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制工程资源需求计划",false,{"key":16,"text":17,"correct":14},"B","应用互联网进行进度控制",{"key":19,"text":20,"correct":21},"C","制定进度控制工作流程",true,{"key":23,"text":24,"correct":14},"D","选择先进的施工技术","2021\u002F2020教材P28页 (1)组织措施。分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，如调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]