[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117657,789,1,"单选题","项目目标动态控制的第一步工作，将项目的目标进行分解，以确定用于目标控制的()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划值",true,{"key":16,"text":17,"correct":18},"B","实际值",false,{"key":20,"text":21,"correct":18},"C","预算值",{"key":23,"text":24,"correct":18},"D","成本值","2021\u002F2020教材P27页 将对项目的目标如投资\u002F成本、进度和质量目标）进行分解，以确定用于目标控制的计划值（如计划投资\u002F成本、计划进度和质量标准等)。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]