[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117656,789,1,"单选题","在项目目标动态控制的工作程序中，第一步的工作是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目决策策划",false,{"key":16,"text":17,"correct":14},"B","制定纠偏措施",{"key":19,"text":20,"correct":21},"C","分解项目目标",true,{"key":23,"text":24,"correct":14},"D","收集实际数据","2021\u002F2020教材P27页 项目目标动态控制的工作程序如下：1. 项目目标动态控制的准备工作，将对项目的目标如投资\u002F成本、进度和质量目标）进行分解，以确定用于目标控制的计划值（如计划投资\u002F成本、计划进度和质量标准等)。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]