[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117655,789,1,"单选题","关于项目目标动态控制的纠偏措施，表述不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经济措施是分析由于经济的原因而影响项目目标实现的问题，并采取相应的措施，包括落实加快工程施工进度所需的资金",false,{"key":16,"text":17,"correct":18},"B","调整进度管理的方法和手段属于纠偏措施中的技术措施",true,{"key":20,"text":21,"correct":14},"C","改变施工管理和强化合同管理属于纠偏措施中的管理措施",{"key":23,"text":24,"correct":14},"D","组织措施是分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，包括管理职能分工、项目管理班子人员","2021\u002F2020教材P28页 调整进度管理的方法和手段，改变施工管理和强化合同管理等属于管理措施。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]