[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117654,789,1,"单选题","施工成本的计划值和实际值的比较不包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程合同价与投标价中的相应成本项的比较",false,{"key":16,"text":17,"correct":14},"B","工程合同价与工程款支付中的相应成本项的比较",{"key":19,"text":20,"correct":21},"C","投标价中的相应成本与实际施工成本中的相应成本项的比较",true,{"key":23,"text":24,"correct":14},"D","施工成本规划与实际施工成本中的相应成本项的比较","2021\u002F2020教材P30页 1. 工程合同价与投标价中相应成本项的比较2、工程合同价与施工成本规划中的相应成本项的比较3、施工成本规划与实际施工成本中的相应成本项的比较4、工程合同价与实际施工成本中的相应成本项的比较5. 工程合同价与工程款支付中相应的成本项比较。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]