[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117653,789,1,"单选题","施工项目技术负责人每天在施工日志上对当天的施工质量和进度情况进行详细记载，属于项目目标动态控制过程中（）的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","准备阶段",false,{"key":16,"text":17,"correct":18},"B","收集项目实际值",true,{"key":20,"text":21,"correct":14},"C","进行目标计划值和实际值比较",{"key":23,"text":24,"correct":14},"D","纠偏环节","2021\u002F2020教材P27页 （1）收集项目目标的实际值，如实际投资\u002F成本、实际施工进度和施工的质量状况等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]