[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117652,789,1,"单选题","在确定了区段工期目标后，为保证项目按期完成，项目经理进一步确定了每月的进度目标。这项工作在运用动态控制原理进行进度控制的工作步骤中，属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将工程进度目标逐层分解",true,{"key":16,"text":17,"correct":18},"B","定期比较工程进度的实际值与计划值",false,{"key":20,"text":21,"correct":18},"C","收集工程进度实际值",{"key":23,"text":24,"correct":18},"D","确定进度控制周期","2021\u002F2020教材P30页 运用动态控制原理控制施工质量的工作步骤与进度控制和成本控制的工作步骤相类似。质量目标不仅是各分部分项工程的施工质量，它还包括材料、半成品、成品和有关设备等的质量。在施工活动开展前，首先应对质量目标进行分解，也即对上述组成工程质量的各元素的质量目标作出明确的定义，它就是质量的计划值。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]