[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117651,789,1,"单选题","在施工成本动态控制过程中，相对于实际施工成本，计划值是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","投标价中的成本值",false,{"key":16,"text":17,"correct":14},"B","工程款支付中的成本值",{"key":19,"text":20,"correct":14},"C","工程合同价",{"key":22,"text":23,"correct":24},"D","施工成本规划的成本值",true,"2021\u002F2020教材P29页 相对于工程合同价而言，施工成本规划的成本值是实际值；而相对于实际施工成本，则施工成本规划的成本值是计划值等。成本的计划值和实际值的比较应是定量的数据比较，比较的成果是成本跟踪和控制报告，如编制成本控制的月、季、半年和年度报告等。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]