[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117648,789,1,"单选题","下列项目目标动态控制的工作中，属于项目目标动态控制准备工作的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将项目的目标进行分解",true,{"key":16,"text":17,"correct":18},"B","收集项目目标的实际值",false,{"key":20,"text":21,"correct":18},"C","对项目目标进行动态跟踪",{"key":23,"text":24,"correct":18},"D","找出实际值与计划值的偏差","2021\u002F2020教材P27页 在项目目标动态控制过程中，要得到用于目标控制的计划值，就必须首先将项目目标进行分解，故选A。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]