[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117646,789,1,"单选题","调整进度管理的方法和手段，属于项目目标动态控制纠偏措施中的( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","管理措施",true,{"key":23,"text":24,"correct":14},"D","经济措施","2021\u002F2020教材P28页 管理措施（包括合同措施），分析由于管理的原因而影响项目目标实现的问题，并采取相应的措施，如调整进度管理的方法和手段，改变施工管理和强化合同管理等。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]