[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117635,789,1,"单选题","为避免项目目标偏离的发生，在项目目标控制工作中采取的主动控制是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进行目标的实际值与计划值比较",false,{"key":16,"text":17,"correct":14},"B","目标出现偏离时采取纠偏措施",{"key":19,"text":20,"correct":21},"C","事前分析可能导致目标偏离的各种影响因素，并采取有效的预防措施",true,{"key":23,"text":24,"correct":14},"D","分析目标的实际值与计划值之间存在偏差的原因","2021\u002F2020教材P28页 为避免项目目标偏离的发生，还应重视事前的主动控制，即事前分析可能导致项目目标偏离的各种影响因素，并针对这些影响因素采取有效的预防措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]