[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117634,789,1,"单选题","在项目目标动态控制的纠偏措施中，加快工程施工进度所需的资金属于()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","管理措施",{"key":19,"text":20,"correct":21},"C","经济措施",true,{"key":23,"text":24,"correct":14},"D","技术措施","2021\u002F2020教材P28页 (3)经济措施。分析由于经济的原因而影响项目目标实现的问题，并采取相应的措施，如落实加快工程施工进度所需的资金等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]