[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117633,789,1,"单选题","在对施工成本目标进行动态跟踪和控制中，应定期对施工成本的()进行比较。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预测值与计划值",false,{"key":16,"text":17,"correct":14},"B","预测值和实际值",{"key":19,"text":20,"correct":21},"C","计划值和实际值",true,{"key":23,"text":24,"correct":14},"D","计划值与定额标准值","2021\u002F2020教材P29页 在施工过程中对施工成本目标进行动态跟踪和控制(1)按照成本控制的要求，收集施工成本的实际值。(2)定期对施工成本的计划值和实际值进行比较。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]