[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117630,789,1,"单选题","调整项目管理人员职责，明确各项管理工作流程，属于项目目标动态控制纠偏措施中的( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","管理措施",false,{"key":20,"text":21,"correct":18},"C","技术措施",{"key":23,"text":24,"correct":18},"D","经济措施","2021\u002F2020教材P28页 项目动态控制的纠偏措施中，涉及组织结构、工作职能分工、工作流程的是组织措施；涉及管理思想、方法、手段、合同管理等的是管理措施；涉及资金、激励等的是经济措施；涉及技术、施工方案等的是技术措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]