[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117629":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117629,789,1,"单选题","调整设计、改进施工方法和改变施工机具等措施属于项目动态控制纠偏措施的( )措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经济",false,{"key":16,"text":17,"correct":14},"B","管理",{"key":19,"text":20,"correct":21},"C","技术",true,{"key":23,"text":24,"correct":14},"D","组织","2021\u002F2020教材P28页 项目目标动态控制的纠偏措施4. 技术措施分析由于技术的原因而影响项目目标实现的问题，并采取相应的措施，如调整设计、改进施工方法和改变施工机具等，",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]