[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117628,789,1,"单选题","( )是工程项目目标动态控制的核心。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","目标的逐层分解",false,{"key":16,"text":17,"correct":14},"B","目标实际数据的收集",{"key":19,"text":20,"correct":21},"C","目标的计划值和实际值的比较，当发现项目目标偏离时采取纠偏措施",true,{"key":23,"text":24,"correct":14},"D","调整项目目标","2021\u002F2020教材P28页 项目目标动态控制的核心是，在项目实施过程中定期地进行项目目标的计划值和实际值的比较，当发现项目目标偏离时采取纠偏措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]