[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117626,789,1,"单选题","在项目实施过程中，为了加强成本管理，对施工方法进行调整优化，改进施工工艺，属于成本控制措施的（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","经济措施",false,{"key":16,"text":17,"correct":14},"B","管理措施",{"key":19,"text":20,"correct":14},"C","组织措施",{"key":22,"text":23,"correct":24},"D","技术措施",true,"2021\u002F2020教材P28页 技术措施中的有关内容，施工方法等关键词可以看出属于技术这一块。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]