[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117625,789,1,"单选题","尽管制定了成本目标，在进行施工成本控制的过程中，针对以下情况，有必要调整施工成本目标的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在施工前没有进一步做更详细的成本策划",false,{"key":16,"text":17,"correct":18},"B","原定的成本目标不合理",true,{"key":20,"text":21,"correct":14},"C","施工实际成本和计划成本略有差异",{"key":23,"text":24,"correct":14},"D","工程款的支付与工程合同价产生偏差","2021\u002F2020教材P27页 需要调整目标的有发现原定的施工成本目标不合理，或原定的施工成本目标无法实现。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]