[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117624":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117624,789,1,"单选题","某施工企业承担了某商务大厦写字楼的土建工程和安装工程施工任务，合同工期626天，在对该项目的施工成本目标进行动态跟踪和控制时，成本的控制周期一般为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","年",false,{"key":16,"text":17,"correct":14},"B","旬",{"key":19,"text":20,"correct":21},"C","月",true,{"key":23,"text":24,"correct":14},"D","半年","2021\u002F2020教材P29页 成本的控制周期应视项目的规模和特点而定，一般的项目控制周期为一个月。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]