[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117623,789,1,"单选题","在施工过程中对施工进度目标进行动态跟踪和控制的工作包括：①收集施工进度实际值；②定期对施工进度的计划值和实际值进行比较；③如有偏差，采取措施进行纠偏。正确的工作流程是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①—②—③",true,{"key":16,"text":17,"correct":18},"B","②—①—③",false,{"key":20,"text":21,"correct":18},"C","②—③—①",{"key":23,"text":24,"correct":18},"D","③—①—②","2021\u002F2020教材P27页 在项目实施过程中（如设计过程中、招投标过程中和施工过程中）对项目目标进行动态跟踪和控制：1、收集项目目标的实际值。2、定期进行项目目标的计划值和实际值的比较。3、通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]