[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117621":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117621,789,1,"单选题","在项目实施过程中，为对工程进度目标进行动态跟踪和控制，在按照进度控制的要求，收集施工进度实际值之后应做的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取措施进行纠偏",false,{"key":16,"text":17,"correct":18},"B","比较工程进度的计划值和实际值",true,{"key":20,"text":21,"correct":14},"C","调整工程进度目标",{"key":23,"text":24,"correct":14},"D","逐层分解工程进度目标","2021\u002F2020教材P27页 收集施工进度实际值之后应做的工作是对工程进度的计划值和实际值进行比较。A是比较后有偏差时应进行的工作；D是收集施工进度实际值之前应做的工作；C是必要时才进行的工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]