[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117619,789,1,"单选题","某施工企业承揽了一项住宅楼施工项目，确定了项目的计划开工日期和竣工日期，并进一步确定了主要分部分项工程的区段工期目标和每月的计划工期。其目的是确定用于目标控制的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","偏差值",false,{"key":16,"text":17,"correct":14},"B","调整值",{"key":19,"text":20,"correct":21},"C","计划值",true,{"key":23,"text":24,"correct":14},"D","实际值","2021\u002F2020教材P27页 在对项目的目标（如投资、成本、进度、质量目标）进行分解，以确定用于目标控制的计划值，建设工程项目目标的动态控制的内容。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]