[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117617,789,1,"单选题","以下属于在项目实施过程中，对项目目标进行动态跟踪和控制的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进行任务分工、规定工作流程",false,{"key":16,"text":17,"correct":14},"B","事前分析可能导致项目目标偏离的各种影响因素",{"key":19,"text":20,"correct":14},"C","针对可能导致项目目标偏离的各种影响因素采取预防措施",{"key":22,"text":23,"correct":24},"D","定期进行项目目标的计划值与实际值的比较",true,"2021\u002F2020教材P27页 属于项目实施过程中对项目目标进行动态跟踪和控制的是： 1、收集项目目标的实际值 2、定期进行项目目标的计划值和实际值的比较 3、通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏差",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]