[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117615,789,1,"单选题","进度的计划值和实际值的比较应是定量的数据比较，比较的成果是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","里程碑事件进度报告",false,{"key":16,"text":17,"correct":14},"B","施工进度计划执行报告",{"key":19,"text":20,"correct":21},"C","进度跟踪和控制报告",true,{"key":23,"text":24,"correct":14},"D","工程进展报告","2021\u002F2020教材P29页 进度的计划值和实际值的比较应是定量的数据比较，比较的成果是进度跟踪和控制报告,如编制进度控制的旬、月、季、半年和年度报告等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]