[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117614,789,1,"单选题","在施工过程中收集组成工程质量的各元素质量的实际值，并定期地对施工质量的计划值和实际值进行跟踪和控制，编制质量控制的()报告。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","旬、月、季和年度",false,{"key":16,"text":17,"correct":14},"B","日、旬、月、季",{"key":19,"text":20,"correct":14},"C","日、旬、半年和年度",{"key":22,"text":23,"correct":24},"D","月、季、半年和年度",true,"2021\u002F2020教材P30页 在施工过程中则应收集上述组成工程质量的各元素质量的实际值，并定期地对施工质量的计划值和实际值进行跟踪和控制，编制质量控制的月、季、半年和年度报告。通过施工质量计划值和实际值的比较，如发现质量的偏差，则必须采取相应的纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]