[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117612,789,1,"单选题","运用动态控制原理控制施工成本时，要定期对施工成本的计划值和实际值进行比较。相对于施工成本规划而言，实际值是指()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程合同价",false,{"key":16,"text":17,"correct":18},"B","实际施工成本",true,{"key":20,"text":21,"correct":14},"C","投标价",{"key":23,"text":24,"correct":14},"D","实际支付的工程款","2021\u002F2020教材P30页 施工成本的计划值和实际值的比较包括：①工程合同价与投标价中的相应成本项的比较；②工程合同价与施工成本规划中的相应成本项的比较；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]