[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117610,789,1,"单选题","下列选项中，属于项目目标控制中主动控制的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","针对可能导致目标偏离的影响因素采取预防措施",true,{"key":16,"text":17,"correct":18},"B","当目标出现偏离时采取行之有效的纠偏措施",false,{"key":20,"text":21,"correct":18},"C","进行目标的实际值与计划值的比较",{"key":23,"text":24,"correct":18},"D","分析目标的实际值与计划值之间存在偏差的原因","2021\u002F2020教材P28页 在项目目标动态控制过程中，为避免目标偏离的发生，应重视事前的主动控制。即事前分析可能导致项目目标偏离的各种影响因素，并针对这些影响因素采取有效的措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]