[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117609,789,1,"单选题","某施工企业承担了某项施工任务，为保证项目目标的实现，项目经理做了以下各项工作，其中属于项目目标事前控制的内容是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","收集项目目标的实际值",false,{"key":16,"text":17,"correct":14},"B","定期进行项目目标的计划值与实际值比较",{"key":19,"text":20,"correct":21},"C","针对影响项目目标的各种因素采取预防措施",true,{"key":23,"text":24,"correct":14},"D","当发现目标偏离时，采取纠偏措施进行纠偏","2021\u002F2020教材P28页 三、项目目标的事前控制项目目标动态控制的核心是，在项目实施的过程中定期地进行项目目标的计划值和实际值的比较，当发现项目目标偏离时采取纠偏措施。为避免项目目标偏离的发生，还应重视事前的主动控制，即事前分析可能导致项目目标偏离的各种影响因素，并针对这些影响因素采取有效的预防措施.",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]