[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117608,789,1,"单选题","在某大型工程项目的施工过程中，由于“下情不能上传，上情不能下达”导致项目经理不能及时作出正确决策，拖延了工期，为了加快施工进度，项目经理修正了信息传递工作流程。这种纠偏措施属于动态控制的（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","技术措施",false,{"key":16,"text":17,"correct":14},"B","管理措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","组织措施",true,"2021\u002F2020教材P28页 (1)组织措施。分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，如调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等。这种题目要看重点词语，修正工作流程即为组织措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]