[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117607,789,1,"单选题","关于项目目标的动态控制，下列说法正确的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目管理最基本的方法论是过程控制论",false,{"key":16,"text":17,"correct":18},"B","项目目标的动态控制的核心是计划值和实际值的定期比较和纠偏",true,{"key":20,"text":21,"correct":14},"C","定期进行目标的计划值和实际值得比较属于主动控制措施",{"key":23,"text":24,"correct":14},"D","事前分析可能导致目标偏离的各种影响因素属于动态控制措施","2021\u002F2020教材P28页 项目目标动态控制的核心是，在项目实施的过程中定期地进行项目目标的计划值和实际值的比较，当发现项目目标偏离时采取纠偏措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]