[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117606":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117606,789,1,"单选题","某施工企业承揽一住宅楼项目施工，在实施的过程中，对项目的进度目标进行动态跟踪和控制，收集施工进度实际值之后应做的工作是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取措施进行纠偏",false,{"key":16,"text":17,"correct":18},"B","比较工程进度的计划值和实际值",true,{"key":20,"text":21,"correct":14},"C","调整工程进度目标",{"key":23,"text":24,"correct":14},"D","逐层分解工程进度目标","2021\u002F2020教材P27页 2. 在项目实施过程中对项目目标进行动态跟踪和控制（1）收集项目目标的实际值（2）定期（如每两周或每月）进行项目目标的计划值和实际值的比较（3）通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]