[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117603,789,1,"单选题","某施工企业承揽了一个住宅施工项目，确定了项目目标的计划值，为了对项目进行动态跟踪和控制，在项目施工过程中，下列各项工作中首先应做的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整项目目标",false,{"key":16,"text":17,"correct":14},"B","比较项目目标的实际值与计划值",{"key":19,"text":20,"correct":21},"C","收集项目目标的实际值",true,{"key":23,"text":24,"correct":14},"D","采取纠偏措施进行纠偏","2021\u002F2020教材P27页 一、动态控制原理2. 在项目实施过程中（如设计过程中、招投标过程中和施工过程中等）对项目目标进行动态跟踪和控制（1）收集项目目标的实际值，如实际投资\u002F成本、实施施工进度和施工的质量状况等；（2）定期（如每两周或每月）进行项目目标的计划值和实际值的比较；（3）通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]