[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117601,789,1,"单选题","项目目标动态控制的组织措施是分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调整进度管理的方法和手段",false,{"key":16,"text":17,"correct":18},"B","调整项目组织结构",true,{"key":20,"text":21,"correct":14},"C","改进施工方法",{"key":23,"text":24,"correct":14},"D","落实加快工程施工进度所需的资金","2021\u002F2020教材P28页 （1）组织措施。分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，如调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]