[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117599,789,1,"单选题","“调整设计、改进施工方法和改变施工机具”属于项目目标动态控制纠偏措施中的( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","管理措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","技术措施",true,"2021\u002F2020教材P28页 4）技术措施。分析由于技术（包括设计和施工技术）的原因而影响项目目标实现的问题，并采取相应的措施，如调整设计、改进施工方法和改变施工机具等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]