[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117598,789,1,"单选题","下列项目目标动态控制措施中，属于管理措施的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","强化合同管理",true,{"key":16,"text":17,"correct":18},"B","调整职能分工",false,{"key":20,"text":21,"correct":18},"C","优化组织结构",{"key":23,"text":24,"correct":18},"D","改进施工工艺","2021\u002F2020教材P28页 (2)管理措施(包括合同措施)。分析由于管理的原因而影响项目目标实现问题，并采取相应措施，如调整进度管理的方法和手段，改变施工管理和强化合同管理等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]