[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117597":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117597,789,1,"单选题","某施工企业在进行施工成本控制时，为了及时了解实施项目的成本情况，需要将计划成本与实际成本相比较，相对于工程合同价而言，属于计划值的是()",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际施工成本",false,{"key":16,"text":17,"correct":14},"B","工程结算款",{"key":19,"text":20,"correct":21},"C","投标价",true,{"key":23,"text":24,"correct":14},"D","工程款支付","2021\u002F2020教材P30页 图2Z101042",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]