[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117595,789,1,"单选题","某建设工程项目经理部根据目标动态控制原理，将项目目标进行了分解，那么在项目目标实施过程中，首先应进行的工作是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定目标控制的计划值",false,{"key":16,"text":17,"correct":14},"B","定期比较目标计划值与实际值",{"key":19,"text":20,"correct":14},"C","分析比较结果，采取纠偏措施",{"key":22,"text":23,"correct":24},"D","收集目标的实际完成值",true,"2021\u002F2020教材P27页 2 在项目实施过程中（如设计过程中、招投标过程中和施工过程中等）对项目目标进行动态跟踪和控制。(1)收集项目目标的实际值，如实际投资成本、实际施工进度和施工的质量状况等；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]