[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117593,789,1,"单选题","施工单位编制分部（分项）工程施工组织设计和季、月、旬施工计划的依据是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织总设计",false,{"key":16,"text":17,"correct":18},"B","单位工程施工组织设计",true,{"key":20,"text":21,"correct":14},"C","单项工程施工组织设计",{"key":23,"text":24,"correct":14},"D","分部（分项）工程施工组织设计","2021\u002F2020教材P25页 单位工程施工组织设计是以单位工程为对象编制的，在施工组织总设计的指导下，由直接组织施工的单位根据施工图设计进行编制，用以直接指导单位工程的施工活动，是施工单位编制分部（分项）工程施工组织设计和季、月、旬施工计划的依据。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]