[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117591,789,1,"单选题","某建筑工程总承包商，承接一高校工程项目的施工任务，其中包括2栋教学楼、1栋试验楼、3栋宿舍楼及其它附属设施，针对该项目施工组织设计的编制，下列选项中表述正确的是()",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","针对教学楼应编制分部分项工程施工组织设计",false,{"key":16,"text":17,"correct":14},"B","针对该高校项目应编制单位工程施工组织设计作为指导全局性施工的技术和经济纲要",{"key":19,"text":20,"correct":14},"C","只有在确定了施工总进度计划后才能编制施工方案",{"key":22,"text":23,"correct":24},"D","如有深基础工程应编制分部分项工程施工组织设计",true,"2021\u002F2020教材P25页 3. 分部（分项）工程施工组织设计的内容如深基础、无粘结预应力混凝土、特大构件的吊装等需要编制分部分项施工组织设计。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]