[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117590,789,1,"单选题","在下列各项工程中，需要直接编制单位工程施工组织设计的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","某市新建机场工程",false,{"key":16,"text":17,"correct":14},"B","某城际高速公路（含公路、桥梁和隧道）",{"key":19,"text":20,"correct":14},"C","某拆除工程定向爆破工程",{"key":22,"text":23,"correct":24},"D","某发电厂干灰库烟囱维修工程",true,"2021\u002F2020教材P24页 本题考查施工组织设计不同层次的分类。新建机场工程和城际高速公路属于整体工程，应编写施工组织总设计、定向爆破应当编写分部(分项)工程施工组织设计，只有某发电厂干灰库烟囱维修工程属于单位工程。故选D。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]