[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117587":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117587,789,1,"单选题","某项目在进行施工组织设计，其中对于施工力量、劳动力、机具、材料、构件等资源供应情况的分析应当属于（）部分的内容",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程概况",true,{"key":16,"text":17,"correct":18},"B","施工部署及施工方案",false,{"key":20,"text":21,"correct":18},"C","施工进度计划",{"key":23,"text":24,"correct":18},"D","主要技术经济指标","2021\u002F2020教材P24页 施工组织设计通常包括工程概况、施工部署及施工方案、施工进度计划、施工平面图及主要技术经济指标。施工力量、劳动力、机具、材料、构件等资源供应情况的分析属于工程概况中的内容。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]