[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117585,789,1,"单选题","施工组织总设计包括如下工作：（1）计算主要工种工程的工程量；（2）编制施工总进度计划；（3）编制资源需求量计划；（4）拟订施工方案。其正确的工作顺序是（）。（2012年真题）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","（1）（2）（3）（4）",false,{"key":16,"text":17,"correct":18},"B","（1）（4）（2）（3）",true,{"key":20,"text":21,"correct":14},"C","（1）（3）（2）（4）",{"key":23,"text":24,"correct":14},"D","（4）（1）（2）（3）","2021\u002F2020教材P26页 施工组织总设计的编制通常采用如下程序：(1)拟订施工方案后才可编制施工总进度计划因为进度的安排取决于施工的方案(2)编制施工总进度计划后才可编制资源需求量计划（因为资源需求量计划要反映各种资源在时间上的需求)。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]