[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117581,789,1,"单选题","编制施工组织总设计时，施工准备工作计划的编制应在完成( )后确定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工准备工作计划",false,{"key":16,"text":17,"correct":14},"B","施工总平面图",{"key":19,"text":20,"correct":21},"C","资源需求量计划",true,{"key":23,"text":24,"correct":14},"D","主要技术经济指标","2021\u002F2020教材P26页 施工组织总设计的编制程序 （1）收集和熟悉编制施工组织总设计所需的有关资料和图纸，进行项目特点和施工条件的调查研究； （2）计算主要工种的工程量； （3）确定施工总体部署； （4）拟定施工方案； （5）编制施工总进度计划； （6）编制资源需求量计划； （7）编制施工准备工作计划； （8）施工总平面图设计； （9）计算主要技术经济指标。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]