[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117580,789,1,"单选题","工程项目施工组织设计中，全面部署施工任务，合理安排施工顺序属于()中的工作内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程概况",false,{"key":16,"text":17,"correct":14},"B","施工总平面图",{"key":19,"text":20,"correct":14},"C","施工进度计划",{"key":22,"text":23,"correct":24},"D","施工部署及施工方案",true,"2021\u002F2020教材P24页 施工部署及施工方案(1)根据工程情况，结合人力、材料、机械设备、资金、施工方法等条件，全面部署施工任务，合理安排施工顺序，确定主要工程的施工方案；(2)对拟建工程可能采用的几个施工方案进行定性、定量的分析，通过技术经济评价，选择最佳方案。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]