[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117577,789,1,"单选题","编制施工组织总设计时，在施工总进度计划确定之后，才可以进行的工作是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拟定施工方案",false,{"key":16,"text":17,"correct":14},"B","确定施工的总体部署",{"key":19,"text":20,"correct":21},"C","编制资源需求量计划",true,{"key":23,"text":24,"correct":14},"D","计算主要工种工程的工程量","2021\u002F2020教材P26页 (2)编制施工总进度计划后才可编制资源需求量计划（因为资源需求量计划反击各种资源在时间上的需求）",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]